An Official Website of the United States Government

Monday, May 20, 2013

Agencywide Documents Access and Management System (ADAMS)

  • Investment Description

    The Agencywide Documents Access and Management System (ADAMS) is the document repository system containing the NRC's unclassified programmatic and administrative records, and collections of documents related to the agency's licensing program, regulatThe Agencywide Documents Access and Management System (ADAMS) is the document repository system containing the NRC's unclassified programmatic and administrative records, and collections of documents related to the agency's licensing program, regulatory activities, and adjudicatory obligations. ADAMS key customers, internal and external stakeholders include the NRC staff, licensees, nuclear industry organizations and groups, general public, and local, state, and federal government agencies. ADAMS is a critical component of the NRC's Enterprise Content Management Program (ECM) that supports the agency's information management needs. ADAMS provides the following mission-critical functions: (1) A document management system to organize, preserve, and retrieve a wealth of documents including regulatory guides, NUREG-series reports, inspection reports, Commission documents, email and correspondence, and other programmatic and administrative material. (2) A recordkeeping system to maintain the agency's official records and manage their timely disposition. (3) An information dissemination system to publish the publicly available documents on the NRC public web site, and to distribute the documents to the agency staff and stakeholders by email. (4) A repository of documents submitted by licensees and other stakeholders through the agency's web-based Electronic Information Exchange (EIE) system. (5) The Electronic Hearing Docket (EHD) document collection which contains publicly available information related to hearings held by the Commission or Atomic Safety Licensing Board Panel (ASLBP). To ensure ADAMS continues to support the NRC mission it was upgraded from the legacy IBM FileNet Content Services platform to the IBM FileNet P8 platform. Benefits of this upgrade include: (1) single sign-on capability; (2) web-based user interface; (3) automation of processes and workflows; (4) improved search tools; and (5) compatibility with a wide array of add-on tools, such as Content Analytics, eDiscovery Manager and Analyzer, Advanced Case Manager, and OmniFind. This E-300 submission provides the justification for the upgrade as a phased implementation of a well integrated portfolio of content management solutions to improve NRC's efficiency and effectiveness. More..

  • FY2013 (CY) Spending

    $3.2 M

    Time frame of Investment

    1999 - 2017

  • Status

    No change in status

CIO Information

Darren B. Ash

Agency Head

Allison M. Macfarlane

Agency

NRC

Bureau

Nuclear Regulatory Commission

Evaluation by Agency CIO

Chart.

Current Evaluation

4

Color balls based on variances or ciorating

Evaluation Explanation

The ADAMS investment completed all but one planned activity for 2012, including the final migration of users from ADAMS Original to ADAMS P8. ADAMS OThe ADAMS investment completed all but one planned activity for 2012, including the final migration of users from ADAMS Original to ADAMS P8. ADAMS Original will be decommissioned in October 2013 upon the migration of the Document Processing Center from ADAMS Original to ADAMS P8. The ADAMS investment successfully completed a TechStat with the focus on budget transparency, clear system definition, costs, roles and responsibilities, maximization of Mission Value, and utilization of existing agency policies and processes. More..

Project Summary

  • Number of Projects

    5

  • Cost Variance

    Chart.

  • Schedule Variance

    Chart.

Project Name Project Life Cycle Costs Cost Variance Schedule Variance
ADAMS Operations and Maintenance, and Document Processing$5.36 MGreenGreen
ADAMS Dependent Applications Migration to FileNET P8 Platform (Phase 2)$1.33 MYellowGreen
ADAMS P8 Administration Utilities Modernization Release 2.1$535.8 KYellowYellow
ADAMS P8 Administration Utilities Modernization Release 2.2$475.2 KRedGreen
ADAMS Dependent Application Migration to FileNet P8 Platform (Phase 1)$1.1 MGreenGreen

Operational Performance

Metric Description Frequency Unit of Measure FY2013 Target Most Recent Actual Met/Not Met Updated Date of Most Recent Actual
Availability of the ADAMS Main Library during operAvailability of the ADAMS Main Library during operating hours. More..Quarterlypercentagepercentage9999Met2013-04-03
Availability of the ADAMS PARS Library during workAvailability of the ADAMS PARS Library during working hours. More..Quarterlypercentagepercentage99100Met2013-04-03
Provide customer support response within 2 dayProvide customer support response within 2 dayQuarterlypercentagepercentage7599Met2013-02-19
Release of non-sensitive, unclassified, regulatoryRelease of non-sensitive, unclassified, regulatory documents internally within 6 days More..Quarterlypercentagepercentage9095Met2013-03-29
Release of non-sensitive, unclassified, regulatoryRelease of non-sensitive, unclassified, regulatory documents to the public within 6 working days. More..Quarterlypercentagepercentage9098Met2013-03-29
Respond to customer inquiries within 1 dayRespond to customer inquiries within 1 dayQuarterlypercentagepercentage9590Met--
Sucessful processing of ADAMS documents into OfficSucessful processing of ADAMS documents into Official Agency Records (OARs). More..Quarterlypercentagepercentage90100Met--
Expand the use of ADAMS custom tools to improve efExpand the use of ADAMS custom tools to improve efficienty throughout the agency. More..Quarterlypercentagepercentage90100Met--
Document Processing Center Scanning StatisticsDocument Processing Center Scanning StatisticsMonthlypercentagepercentage90100Met2013-04-15

Related URLs

Category URL
Related DatasetsRelated Datasetshttp://www.nrc.gov/reading-rm/adams.html
Related APIRelated APIhttp://www.nrc.gov/reading-rm/adams.html

The (No) symbol indicates the link is broken or not publicly available.



Other Investment Metrics

Category Value
Does the investment have any activities with a planned duration greater than a year?:No
Planned duration of the longest activity (days):183
Average planned duration of in-progress and future activities (days):144
Planned cost of one activity is greater than 25% of total planned cost of all activities?:No
Number of contracts applying modular development principles:0

All activity calculations assess only activities with no related child activities.



Note: All descriptions, dates, and costs are as reported by agencies.

More details about Investment Dashboard