Skip to main content
U.S. flag

An official website of the United States government

Investment Details

View Business Case HTML

Investment Description

RSS is a consolidated investment containing multiple systems and applications to support the two primary missions of the Retail program: (1) sell and service U.S. Treasury securities held directly by private individuals and organizations, and (2) manage the Judgment Fund appropriation used to pay most court settlements and Justice Department compromise settlements against the United States.
Agency Department of the Treasury
Point of Contact Tony Arcadi - CIO email Not Provided
Investment Type Major IT Investments
Bureau Fiscal Service
Mission Support Not Applicable
Shared Service Category Not Applicable
Shared Service Identifier Not Applicable
TMF Initiatives
  • Not Applicable
FY 2024 IT Spending $120.13 M
Current CIO Rating 3
Data As Of: 03/29/2024

Total Projects

5

Cost Variance

  • 5Low
  • 0Medium
  • 0High

Schedule Variance

  • 3Low
  • 2Medium
  • 0High

Cost Variance

  • Low: Projects that have <10% Cost Variance
  • Medium: Projects that have ≥10% and <30% Cost Variance
  • High: Projects that have ≥30% Cost Variance
Cost Variance: ((Planned Total Costs - Projected or Actual Total Costs) / Planned Total Cost) x 100

Schedule Variance

  • Low: Projects that have <10% Schedule Variance
  • Medium: Projects that have ≥10% and <30% Schedule Variance
  • High: Projects that have ≥30% Schedule Variance
Schedule Variance: ((Planned Completion Date - Projected or Actual Completion Date) / Project Duration) x 100
  • This section displays the Chief Information Officer (CIO) Risk ratings for the investment. CIOs rate each investment using a set of pre-established criteria and issue a CIO Evaluation Number that reflects the investment’s ability to accomplish its goals within the current fiscal year. This number ranges from 1 - 5, and the higher it is, the better the investment has been rated to meet its goals.
    CIO Rating Date Comments
    3 Mar 29, 2024 CV: SV: OMV: 3.38% OVERALL: -8.31% (Green) The percentage of calls answered within five minutes was the only metric not to reach a result within a tolerable range (67% vs 80% target.) The call volumes were elevated this month due to purchase limit resets and the start of tax season. As previously reported - the volume of incoming case work continues to compromise customer servicing performance. Incoming redemption cases continue to exceed levels above the staff’s capacity. (03/29/2024).
    3 Feb 28, 2024 CV: SV: OMV: 3.95% OVERALL: -8.03% (Green) The percentage of calls answered within five minutes was the only metric not to reach a result within a tolerable range. The call volumes were elevated this month due to purchase limit resets and the start of tax season. As previously reported - the volume of incoming case work continues to compromise customer servicing performance. Incoming redemption cases continue to exceed levels above the staff’s capacity. (02/28/2024).
    3 Jan 31, 2024 CV: SV: OMV: 8.83% OVERALL: -5.58% (Green) The investment met or was within tolerable variance of the performance goals for its key metrics. The volume of incoming case work continues to compromise customer servicing performance. Incoming redemption cases continue to exceed levels above the staff’s capacity. During the next several months, a plan has been put into place to move resources to focus on complex cases to reduce the complex inventory bucket. (01/31/2024).
    3 Dec 04, 2023 CV: SV: OMV: 8.83% OVERALL: -5.58% (Green) Improvement from Oct as investment was rebaselined. Volume of incoming case work continues to compromise customer servicing performance. Interest rates for Series I savings bond have dropped, cooling workload related to new security sales; incoming redemption cases continue to exceed levels above staff capacity. Decreasing participation rates of private financial institutions to process savings bond redemptions increases caseload. (12/04/2023).
    3 Oct 30, 2023 CV: -65.24% SV: 1.58% OMV: 9.50% OVERALL: -18.54% (Yellow) The TRIM project schedule has been changed to accommodate evolving business requirement. The new proposed baseline has not been approved by the Bureau’s Governance boards. Consequently, the project’s baseline in SPIKE cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. So, further updates cannot be provided until the baseline in SPIKE has been updated. (10/30/2023).
    3 Sep 28, 2023 CV: -65.24% SV: 1.58% OMV: 8.83% OVERALL: -18.71% (Yellow) The TRIM project schedule has been changed to accommodate evolving business requirements. The new proposed baseline has not been approved by the Bureau’s Governance boards, thus the project’s baseline cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. Further updates cannot be provided until the baseline in SPIKE has been updated. 2 of 5 metrics are red. (09/28/2023).
    3 Aug 29, 2023 CV: -65.24% SV: 1.58% OMV: 8.83% OVERALL: -18.54% (Yellow) The TRIM project schedule (reason for the SV) has been changed to accommodate evolving business requirements. The new proposed baseline has not been approved by the Bureau’s Governance boards, thus the project’s baseline in SPIKE cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. Further updates cannot be provided until the baseline in SPIKE has been updated. (08/29/2023).
    3 Jul 25, 2023 CV: -65.24% SV: 1.58% OMV: 9.50% OVERALL: -18.54% (Yellow) Volume of in-coming case work continues to compromise customer servicing performance. Interest rates for Series I savings bonds has dropped, cooling workload related to new security sales; incoming redemption cases continue to exceed levels above the staff’s capacity. Retail received Governance approval to hire additional CS staff to handle increased workload. Efforts initiated to hire and onboard new staff members. (07/25/2023).
    3 Jun 30, 2023 CV: -65.24% SV: 1.58% OMV: 9.50% OVERALL: -18.54% (Yellow) BCIO Rating lowered to 1 due to lack of visibility into long-term business strategy and reqmts for moving legacy systems off Mainframe to include decommissioning of Treasury Direct. High risk to the TRIM/MyTreasury project due to ongoing challenges related to delivery of core functionality, coding, defects, testing, and environments. IVV underway to assess opportunities to improve processes and controls. (06/30/2023).
    3 May 30, 2023 CV: -65.24% SV: 1.58% OMV: 10.33% OVERALL: -18.33% (Yellow) Variances: The TRIM project schedule has been changed to accommodate evolving business reqmts. The new proposed baseline has not been approved by the Bureau’s Governance boards. Consequently, the project’s baseline in SPIKE cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. So, further updates cannot be provided until the baseline in SPIKE has been updated. (05/30/2023).
    3 Apr 26, 2023 CV: -65.24% SV: 1.58% OMV: 10.33% OVERALL: -18.33% (Yellow) Variances: The TRIM project schedule has been changed to accommodate evolving business reqmts. The new proposed baseline has not been approved by the Bureau’s Governance boards. Consequently, the project’s baseline in SPIKE cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. So, further updates cannot be provided until the baseline in SPIKE has been updated. (04/26/2023).
    4 Mar 28, 2023 CV: -76.60% SV: -22.89% OMV: 11.17% OVERALL: -23.96% (Yellow) The TRIM project schedule has been changed to accommodate evolving business requirement. The new proposed baseline has not been approved by the Bureau’s Governance boards. Consequently, the project’s baseline in SPIKE cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. So, further updates cannot be provided until the baseline in SPIKE has been updated. (03/28/2023).
    4 Feb 28, 2023 CV: -76.15% SV: -27.11% OMV: 10.50% OVERALL: -25.07% (Yellow) the TRIM project schedule has been changed to accommodate evolving business requirement. The new proposed baseline has not been approved by the Bureau’s Governance boards. Consequently, the project’s baseline in SPIKE cannot be updated until approval is granted. The revised schedule has superseded the current baseline in SPIKE. So, further updates cannot be provided until the baseline in SPIKE has been updated. (02/28/2023).
    4 Jan 25, 2023 CV: -76.15% SV: -27.11% OMV: 11.00% OVERALL: -24.94% (Yellow) The development velocity of the TRIM project Rel 1 Marketables Security functionality is significantly less than projected, based on Jan 2019 projections. This is due in large part to staffing challenges resulting from the "Great Resignation" national work environment. Additional budget requirements are being discussed in July thru Sept. New velocity baseline will be established following Sept ESB. (01/25/2023).
    4 Dec 22, 2022 CV: -76.15% SV: -27.11% OMV: 16.67% OVERALL: -23.52% (Yellow) Cost variance due to a change in the IT service provider’s cost allocation method (the Federal Reserve). Overhead and indirect costs are now allocated down to the project and activity level, which was not done when the baseline’s costs were estimated. This change has increased the cost for all Bureau customers of the Federal Reserve. Schedule variance due to the TRIM project, which is being rebaselined. (12/22/2022).
    4 Nov 22, 2022 CV: -91.98% SV: -27.11% OMV: 24.17% OVERALL: -25.61% (Yellow) PPMI remains RED. The program is in the process of reconciling variables that have deteriorated the current program status for scope and budget from yellow to red, also impacting previously communicated Get to Green plan activities. Key program stakeholders met in person in June to determine appropriate path forward. All work beyond the current planned check functionality is paused alternatives evaluation. (11/22/2022).
    4 Oct 25, 2022 CV: -1.12% SV: -51.03% OMV: -18.30% OVERALL: -19.49% (Yellow) The high SV is being caused by recent changes in the schedule for the TRIM project. An error in the baseline has generated a false-negative variance of -231 days. Once reliable financial forecasts for the project are made available, a BCR to update the baseline and correct errors will be submitted. The high OMV is being caused by degradation in several of the investment’s customer service metrics. (10/25/2022).
    4 Sep 29, 2022 CV: -1.12% SV: -47.39% OMV: -17.80% OVERALL: -18.45% (Yellow) SV caused by recent changes in TRIM project schedule. Tentatively approved mitigation shifted milestone completion dates from early May to mid-Oct 2022. In addition, there was an entry error resulting in a SV that will be addressed with a BCR. High OMV caused by degradation in investment’s customer service metrics. Please see Bureau comment for more detail. (09/29/2022).
    4 Aug 23, 2022 CV: -1.12% SV: -43.62% OMV: -16.68% OVERALL: -17.23% (Yellow) Unchanged from July: SV caused by recent changes in TRIM project schedule. Tentatively approved mitigation shifted milestone completion dates from early May to mid-Oct 2022. In addition, there was an entry error resulting in a SV that will be addressed with a BCR. High OMV caused by degradation in investment’s customer service metrics. Please see Bureau comment for more detail. (08/23/2022).
    4 Jul 25, 2022 CV: -1.12% SV: -39.85% OMV: -15.64% OVERALL: -16.03% (Yellow) SV caused by recent changes in TRIM project schedule. Tentatively approved mitigation shifted milestone completion dates from early May to mid-Oct 2022. In addition, there was an entry error resulting in a SV that will be addressed with a BCR. High OMV caused by degradation in investment’s customer service metrics. Please see Bureau comment for more detail. (07/25/2022).
    4 Jun 22, 2022 CV: -1.12% SV: -36.21% OMV: -12.39% OVERALL: -14.31% (Yellow) SV caused by recent changes in TRIM project schedule. Tentatively approved mitigation shifted milestone completion dates from early May to mid-Oct 2022. The “MUD Solution Project also has a significant SV. High OMV caused by degradation in investment’s customer service metrics. Retail customer service has encountered a significant increase in workload triggered by high interest rates for Series I savings bonds. (06/22/2022).
    4 May 31, 2022 CV: -1.12% SV: -32.44% OMV: -9.86% OVERALL: -12.73% (Yellow) SV is caused by recent changes in the schedule for the TRIM and MUD projects. The tentatively approved mitigation has shifted milestone completion dates from early May to mid-Oct 2022. High OMV is caused by degradation in the investment’s customer service metrics. Retail customer service has encountered a significant increase in workload triggered by high interest rates for the Series I savings bonds. (05/25/2022).
    4 Apr 22, 2022 CV: -1.12% SV: -8.63% OMV: -4.54% OVERALL: -5.45% (Green) Two metrics performing poorly: % Cases Processed within SLO yellow; Cases that Can Still Meet SLO is red. Both affected by workload increase triggered by high interest rate for Series I savings bond. This situation is further compounded by the usual spike in customer calls during tax season. TRIM project activity, Rel 1 Deployment, has not begun. This activity should have been deleted when the BY23 BCR was created. (04/21/2022).
  • The Investment Details section views help answer questions about how an investment's financial resources are being utilized, and which funds are being assigned.
  • The IT spending visualization below provides the selected IT investment's spending over 5 fiscal years. The IT Investment's spending is further broken down by Operations & Maintenance (O&M) and Development, Modernization, and Enhancement (DME). For each listed fiscal year you will see:
    • Requested amount - The IT $ amount the agency requested from Congress in the President's budget request for that fiscal year.
    • Enacted amount - The IT $ amount Congress actually funded through that fiscal year's appropriation.
    • Actual amount - The IT $ amount the agency actually spent that fiscal year based on what was appropriated by Congress.
    The availability of data for each fiscal year will depend on where in the federal budget process we currently are, and will continue to be updated as the annual appropriations process progresses.

  • Project Name Project UID Status Project Life Cycle Cost ($M) Cost Variance (%) Start Date End Date Schedule Variance (%) Schedule Variance (Days) TMF Initiative
    Accrual Bond Payment System (ABPS) Project 202050 Complete 0 7.7 2018-06-17 2021-01-02 29 29 Not Applicable
    Treasury Retail Investment Manager (TRIM) 202284 In Progress 0 0 2019-01-19 0 0 Not Applicable
    Matured & Unredeemed Debt (MUD) Solution 202436 Completed 0 0 2020-10-01 2023-01-27 2.8 2.8 Not Applicable
    REGII Mainframe Migration 202757 In Progress 0 0 2022-06-07 -20 -20 Not Applicable
    SBVV - Fraud 202758 In Progress 0 0 2023-10-19 0 0 Not Applicable
    LowMediumHigh
  • Metric Description Performance Measurement Category Unit of Measure Reporting Frequency Agency Baseline Capability Measurement Condition Target 2024 CY Latest Actual Result Date of Latest Actual Result Met Target
    Average number of business days for basic cases to go from open to closed status (Average Case Resolution time) Strategic and Business Results days Monthly Under target 30 27 2024-03-29 18:53:08 MET
    Percentage of calls answered within 5 minutes. Customer Satisfaction percent Monthly Over target 80 67 2024-03-29 18:53:09 NOT MET
    Average number of business days for complex cases to go from open to closed status (Average Case Resolution time) Strategic and Business Results days Monthly Under target 90 82 2024-03-29 18:53:09 MET
    Percent of Security Payments Processed Accurately and Timely Financial Performance Percent Monthly Over target 100 2024-03-29 18:53:07 MET
    Percentage of cases that can still meet assigned 40 day SLO in the current inventory (Cases Meeting Days Assigned, based off Receipt Date) Strategic and Business Results Percent Monthly 80 Over target 80 2023-04-26 22:45:42 MET
    Percent of Unassisted Retail Securities Transaction Strategic and Business Results Percent Monthly 73 Over target 83.2 2024-03-29 18:53:06 MET
    Percent of Domestic Judgment Fund Payments Processed within Service Level Objective Strategic and Business Results Percent Monthly 85 Over target 86 2024-03-29 18:53:07 MET